Heritage House Condominium Association
Updates on Reconstruction
From the Heritage House Condominium Association Board of Directors
February
2, 2007
FR: Jim Driscoll
Nyman Construction
RE: Construction Progress Update
DATE: January 29, 2007
A
complete set of architectural and engineering prints was reviewed and approved
by the City of
The Board of Directors has authorized Nyman Construction to begin the installation of the new sprinkler system. The work began January 22nd and the rough-ins should be completed by the end of February. For owners in the undamaged portion of the building, it will be necessary to selectively cut holes in the ceilings in order to install the sprinklers. All the holes will be patched and repainted.
State Auto Insurance has approved the new elevators and we are working with the Board of Directors to finalize the contract.