Heritage House Condominium Association
Updates on Reconstruction
From the Heritage House Condominium Association Board of Directors
March 7, 2007
FR: Jim Driscoll, Nyman Construction
RE: Construction Progress Update
DATE: March 6, 2007
The Board of Directors authorized Nyman Construction to
proceed with the following three contracts.
The first contract was for the sprinklers as ordered by the City of
The sprinkler work began in early February. The rough-in portion of the work should be completed with in two to three weeks.
The fire alarm wiring installation is scheduled to begin this month. Smoke detectors are required in all residential units. The detectors are combination heat and smoke detectors.
Nyman has ordered the new elevators. Work has begun on the existing elevator shafts to remove all the old equipment and to prepare the shafts to accept the new equipment.
Hoping to get a jump on the unit reconstruction, Nyman Construction has taken it upon them selves to award a contract to their HVAC contractor. Said contractor began working this week to install duct work in the third floor units. Nyman also started painting the interior masonry walls in units 301-316 prior to the drywall being installed.
Nyman Construction is hopeful of being able to take one unit on the first floor near the lobby elevator and ready it as a model suite for all to see before unit owners select any finishes: paint, flooring, lighting, counters, cabinets, etc. The finish items will consist of items that were approved by State Auto. If individual finish items are not acceptable to a particular owner or they wish to upgrade an item, a credit will be issued. Said credit can be applied toward owner selected finish items or upgrades.
The next step for Jim will be to meet with the remaining unit owners – South End - to get their input into any changes they might like to make while their units are vacant.